Thermal Release Request
The Department requests an increase in the thermal enhancement to 700 cfs starting at 2:00 PM July 5th to 4:00 AM July 6th, then a return to 550 cfs starting at 4:00 AM until 4:00 PM tomorrow or until tomorrow’s design is complete. The increase and decrease may be made in two steps each.
About 1,600 cfs-days remain in the Thermal Mitigation Bank at the time of this request.
Cannonsville Reservoir Requested Ramping Schedule
July 5
Time | Beginning Flow (cfs) |
Ending Flow (cfs) |
Loss/Gain (cfs) |
---|---|---|---|
2:00 PM | 550 | 700 | +150 |
The increase and decrease may be made in two steps each. |
July 6
Time | Beginning Flow (cfs) |
Ending Flow (cfs) |
Loss/Gain (cfs) |
---|---|---|---|
4:00 AM | 700 | 550 | -150 |
Requested By:
Brenan Tarrier
Professional Engineer 1, Division of Water
New York State Department of Environmental Conservation